39Procure renewable electricity from third party producers.

Progress

Work is proceeding
  • Not started
  • Initiated
  • Development
  • Implementation
  • Operations
  • Complete
Target Indicator: 1600 MW of renewable electrical capacity procured by 2050.

Progress Update

An expression of interest was submitted to SaskPower for participation in their new Renewable Partnership Offering, for purchase of 66 MW of solar power. Updates on the program and costing are anticipated in 2024 and 2025, following which decisions on participation and funding sources will be made.

Past Progress on this Action

Report: 1.1.2021 31.12.2021
2021 Climate Action Progress Report

Progress Update

No progress.

Tasks

What's left to do?

  • Todo12/31/2028

    Alternatives to meet GHG targets

    Responsible party: TBD

What are we doing?

  • Todo12/31/2023

    Procure renewable energy over time to meet targets

    Responsible party: SL&P/ SUST

  • Todo12/31/2023

    RPO opportunity with SaskPower

    Responsible party: SL&P

Indicators

Summary and contacts

Timeline

1/1/2040 →

Action target audience

Information updated 05.12.2024