37Construct a hydropower plant at the Weir.

Progress

Work has not started and behind planned timeframe
  • Not started
  • Initiated
  • Development
  • Implementation
  • Operations
  • Complete
Target Indicator: 6 MW of hydropower capacity installed at the weir with an operational efficiency of 55% or greater by 2027.

Progress Update

On hold unless adequate funding and/or partnerships become available. A reassessment of the project to determine its viability is tentatively planned for 2026.

Past Progress on this Action

Report: 1/1/2021 12/31/2021
2021 Climate Action Progress Report

Progress Update

On hold unless adequate funding and/or partnerships become available.

Tasks

What's left to do?

  • Todo12/31/2027

    Install hydropower at the weir to meet targets

    Responsible party: SL&P

  • Todo12/31/2028

    Alternatives to meet GHG targets

    Responsible party: TBD