1Apply energy efficiency standards (build to Passive House) to all new municipal buildings.

Progress

Work is behind LEC/Adaptation timeframe
  • Not started
  • Initiated
  • Development
  • Implementation
  • Operations
  • Complete
  • Cancelled
Target Indicator: 100% of new buildings meet the Passive House/Net-zero Energy-ready standard immediately (2020).

Report card

Report: 1.1.2021 31.12.2021
Progress Report Card 2021

Progress Update

High Performance Civic Building Policy enacted 2022 and requires new buildings be Net-zero Energy-ready. Fire Hall Five is LEED Certified (not Passive House / Net-zero Energy-ready)4. No buildings have started the design phase since January 2022 (when policy passed).

Description

Progress Update

High Performance Civic Building Policy C08-002 enacted on January 1, 2022, requiring new municipal buildings to be Net-zero Energy-ready. Construction of Fire Hall #5 (LEED Certified) commenced in April 2022, and a ceremonial grand opening event was held in August 2023. No buildings have started the design phase since the policy was enacted in January 2022.

Official description

Apply energy efficiency standards (build to Passive House) to all new municipal buildings
(According to the action plan)

Summary and contacts

Timeline

1/1/2020 →

Action target audience

Lead Departments

Information updated 08.05.2024

How this action contributes to the outcome